and advertisement for bids, and are tabulated below. <br />Contractor Bid <br />North Valley, Inc. $132,179.97 <br />Diversified Paving $201,170.00 <br />TAG Asphalt and Concrete $174,415.00 <br />Asphalt Surface Technologies Corp. $213,872.10 <br />Hanson Paving $257,698.35 <br />Engineer's Estimate $180, 000.00 <br />The lowest responsible bid was submitted by North Valley, Inc. of Nowthen, Minnesota, in the amount of <br />$132,179.97 for the total bid for construction of the improvements in accordance with the approved plans and <br />specifications and advertisement for bids. <br />Notification: <br />Advertisements for bids appeared in the Anoka Union Herald on June 27th and July 4th. <br />Bids were opened publicly on August 5th. <br />Time Frame/Observations/Alternatives: <br />Observations: <br />Based on staffs observations of all contracted skim patching work to date, skim patching is anticipated to have a <br />useful life of at least 3 years, and likely much more. To date, this product is holding up very well to plowing, <br />traffic and weather. <br />Tentative project schedule: <br />• August 12th - Council considers award of contract <br />• Mid -August - Start construction <br />• September 26th - Final completion <br />City staff will continue patching all remaining public paved street segments in-house as time allows. <br />Alternatives: <br />Alternative #1: Motion to adopt Resolution #25-176 accepting bids and awarding a construction contract for 2025 <br />Pavement Skim Patching, Maintenance Project #25-56. <br />Alternative #2: Motion of other. <br />Funding Source: <br />Payment for this work is proposed to come from the $600,000 budgeted for 2025 cracksealing, pavement <br />rejuvenator, and pavement patching projects. A total of $176,000 remains available for 2025 skim patching <br />contracted services. <br />Recommendation: <br />Staff recommends Alternative #1. <br />Outcome/Action: <br />Adopt Resolution #25-176 accepting bids and awarding a construction contract for 2025 Pavement Skim <br />Patching, Maintenance Project #25-56, to North Valley, Inc. in the amount of $132,179.97. <br />