CC Regular Session <br />Meeting Date: <br />09/23/2025 <br />Primary Strategic Plan Initiative: Improve the safety and mobility of transportation corridors. <br />5. 12. <br />Title: <br />Adopt Resolution #25-227 Approving Change Order #1 for 2025 Neighborhood Pavement Overlay <br />Improvements, Improvement Project #25-07 <br />Purpose/Background: <br />Purpose: <br />The purpose of this case is to adopt Resolution #25-227 approving Change Order #1 for 2025 Neighborhood <br />Pavement Overlay Improvements, Improvement Project #25-07. Change Order #1 is necessary to re -place <br />pavement markings within the project limits. <br />Background: <br />Numerous streets with the project had existing pavement markings, delineating parking lanes, center lines and <br />pedestrian crosswalks within streets in the Ramsey Town Center subdivisions. Additionally, existing pedestrian <br />crosswalk markings at trail crossings within the Rum River Hills subdivision. <br />The construction bid set of plans did not include replacing the existing pavement markings Change Order #1 <br />adds the pavement markings into the plans, matching the original layouts. These pavement markings are <br />necessary safety improvements, a set of pavement marking plans is attached to this case for reference. <br />Notification: <br />Notification is not required. <br />Time Frame/Observations/Alternatives: <br />Observations: <br />Ideally, the pavement marking plan sheets would have been included in the plan set at the time of bidding. In the <br />future, staff will make a more comprehensive effort to make holistic plan set reviews a priority to avoid change <br />orders of this nature. Both staff and the contractor did not recognize pavement marking quantities were not <br />included in the construction plan bid quantities in time to provide a change order prior to the work occurring. <br />Pavement markings were placed during the week of September 15th so this request for approval is occurring after <br />the work was completed. <br />Staff has reviewed the unit prices for the change order and feels the prices are reasonable based on current <br />construction costs. <br />Alternatives: <br />Motion to adopt Resolution #25-227 approving Change Order #1 for 2025 Neighborhood Pavement Overlay <br />Improvements, Improvement Project #25-07. <br />Funding Source: <br />Funding for this improvement is proposed to come from Pavement Management Funds. Change Order #1 <br />increases the construction costs by $26,301.62. <br />Recommendation: <br />