TABLE 2 <br /> <br />COST SUMMARY <br /> <br />Total project cost <br /> <br />Total units assessed <br /> <br />Cost per unk <br /> <br />Annual assessment cost <br />(10 years @ 8%) <br /> <br />PROJECT SCHEDULE <br /> <br />If the City wishes to proceed with these improvements, <br />anticipated: <br /> <br /> Accept feasibility study and set public hearing <br /> <br /> Hold public hearing <br /> <br /> Order project, authorize plans and specifications <br /> and request bids <br /> <br /> Openb bids <br /> <br /> Recieve bids and award project <br /> <br /> Begin construction <br /> <br /> Complete construction <br /> <br /> Hold assessment hearing <br /> <br /> First payments due <br /> <br />$17,680 <br />8 <br />2,210 <br />329.36 <br /> <br />the following schedule could be <br /> <br />July 13, 1993 <br />July 27, 1993 <br /> <br />September 28,1993 <br />October 10, 1993 <br />October 12,1993 <br />October 1993 <br />October 1993 <br /> <br />1994 <br /> <br />Spring 1995 <br /> <br /> <br />