Laserfiche WebLink
6. PROJECT SCHEDULE <br />The proposed project schedule is as follows: <br />Council Orders Feasibility Report January 12, 2016 <br />Public Works Committee Reviews Feasibility Report February 16, 2016 <br />Council Accepts Feasibility Report/Authorizes Plans and Specifications February 23, 2016 <br />Staff Conducts Private Utility Coordination Meeting March, 2016 <br />Council Approves Plans and Specifications/Authorizes Ad for Bids April 12, 2016 <br />Staff Receives Bids May 17, 2016 <br />Council Awards Contract May 24, 2016 <br />Contractor Begins Construction June 2016 <br />Contractor Completes Construction October 2016 <br />Feasibility Report <br />Business Park 95 Regional Stonnwater Pond Outlet Improvements <br />City of Ramsey Project No. 16-36 <br />Page 7 <br />