SECTION 01330 — SUBMITTALS <br />PART 1-- GENERAL <br />1.1 SUMMARY <br />A. The Contractor shall submit three (3) copies of all required submittals and sample items as noted below. <br />The Engineer will review them with reasonable promptness. The Contractor shall make all required <br />corrections and file with the Engineer three (3) corrected sets for final review. If the Contractor requires <br />more than two (2) reviewed copies, the Contractor shall submit additional sets. <br />B. The responsibility for completeness of submittals lies with the Contractor. If the Engineer and/or Owner <br />sign the submittal with no exception taken, such action shall not absolve the responsibilities of the <br />Contractor in any way. <br />C. Emailed submittals to the Engineer in pdf format will be accepted. <br />1.2 ITEMS TO BE SUBMITTED <br />1. Written Progress Management Schedule Tool (as defined in Section 01310) - to be reviewed at the <br />Preconstruction Conference. See Article 4 of 00520 Agreement for contractual time requirements. <br />2. Minnesota Pollution Control Agency (MPCA) - General Storm Water Permit for Construction Activity <br />(MN R100001) — Reference Section 02370— Erosion & Sediment Control. <br />3. Concrete Mix Design <br />4. Bituminous Mix Design (wear and non -wear) <br />5. Gradation Test Results from 2 separate tests, as required in Source Quality Control provisions of <br />individual sections contained herein, from material stockpiles of aggregates to be used on this project. <br />These tests may be run by the Contractor or its supplier during aggregate production. <br />6. Geotextile Fabrics - Certificates of Compliance. <br />7. Storm Sewer <br />(a) Manhole and catch basin structure - shop drawings. <br />(b) Manhole and catch basin casting - shop drawings. <br />(c) Piping and fittings - Certificates of Compliance. <br />8. Watermain and Water Service Lines <br />(a) Hydrants - Certificates of Compliance. <br />(b) Valves & boxes - Certificates of Compliance. <br />(c) Pipe & fittings - Certificates of Compliance. <br />9. Seeding - Certificates of Compliance for seed mixture. <br />1.3 MATERIAL SAFETY DATA SHEETS <br />A. The Contractor shall submit two copies of Safety Data Sheets (SDSs) (formerly known as Material Safety <br />Data Sheets or MSDSs) for each material on site to the OWNER. <br />B. The Contractor shall maintain an orderly file of material safety data sheets at the job site. <br />City of Ramsey - R16.111092 <br />April 5, 2017 <br />SUBMITTALS <br />PAGE 01330-1 <br />V062612 © Bolton & Menk, Inc. 2016, All Rights Reserved <br />