SECTION 01720 - FIELD ENGINEERING <br />PART 1-- -- GENERAL <br />1.1 STAKING <br />A. Unless otherwise specified in the specific sections, Owner shall provide engineering surveys to establish <br />reference points for construction as follows: <br />1. Storm Sewer: Staking will be furnished and set by the Engineer at 50 foot spacing (usually offset for <br />construction) for the control of the underground construction herein described. Cuts to the proposed <br />pipeline grade will be furnished by the Engineer. Manholes and catch basins will be staked with an <br />offset and a witness with a cut to the lowest structure invert. <br />2. Watermain: The staking interval for watermain shall be 50 feet. Cuts to the proposed pipeline grade <br />will be furnished by the Engineer. Location staking shall be provided for valves and fittings. Hydrants <br />will be staked with an offset and a witness with a cut to the ground elevation at the hydrant. <br />3. Street Grading and Top of Curb: A control line (usually offset from the curb line) with cuts and fills to <br />proposed grade at 50 foot spacing on tangents, and 25 foot spacing on horizontal or vertical curves, <br />shall be furnished and set on both sides for control of the construction herein described. <br />4. Site Grading: Centerline stakes, with cut or fill to finished grade will be provided at 50 foot spacing. <br />Stakes with cut or fill to finished grade will be provided for; contours representing grade breaks at 100 <br />foot spacing along the contour, contours representing the top and bottom of ponds at 100 foot spacing <br />along the contour, and for building pad corners (usually offset from the actual corner). <br />5. The Contractor shall give the Engineer sufficient notice, normally two working days, to provide staking <br />for the orderly progress of the work and shall provide clear line of sight for all staking. <br />6. The stakes are an integral part of the project and the Contractor shall protect and preserve all such <br />stakes and marks, and may be charged with the expense of resetting all such stakes and marks <br />destroyed or disturbed due to the Contractor's carelessness or negligence. Stakes that are destroyed <br />due to vandalism, erosion or other incidents shall be re -staked by the Engineer, at the Contractor's <br />expense. <br />7. In the event of apparent or questionable errors or inconsistencies in such stakes set for control of line <br />and/or grade, the Contractor shall promptly notify the Engineer of such error or inconsistency and shall <br />not proceed with the work until such stake, grade, or mark shall have been verified or corrected by the <br />Engineer. <br />8. All other line and grade staking shall be the responsibility of the Contractor. The Contractor shall <br />furnish sufficient equipment and personnel for determination of plan grades, cross sections, course <br />thicknesses, etc. The survey cost of establishing stakes requested by the Contractor for the <br />convenience of the Contractor, beyond those cited as basic project control, will be charged to the <br />Contractor or withheld from the amounts due to the Contractor. <br />B. Unless otherwise stated in the applicable section of the Specifications or waived by the Engineer, the <br />Contractor shall provide Blue Tops prior to final paving for subgrade and aggregate base construction. <br />1.2 SPECIFICATION <br />A. Water Distribution System - See CEAM 2600.3 (A2). <br />B. Pipe Sewers - See CEAM 2621.3 (A2). <br />PART 2 -- PRODUCTS (NOT USED) <br />PART 3 -- EXECUTION (NOT USED) <br />City of Ramsey - R16.111092 <br />April 5, 2017 <br />****END OF SECTION**** <br />FIELD ENGINEERING <br />PAGE 01720-1 <br />V040110 © Bolton & Menk, Inc. 2016, All Rights Reserved <br />