Project schedule <br /> March 8th—Accept bids/Award contract <br /> Start of Construction-TBD <br /> Substantial Completion Fall 2022 <br /> Time Frame/Observations/Alternatives: <br /> Observations: <br /> With the construction of the salt storage building at the new PW site, all PW functions will be centralized at one <br /> location,with the exception of tree/brush recycling, which will continue to operate out of the former site. Locating <br /> the salt storage building at the new site will provide additional operational efficiencies by eliminating the travel <br /> time for staff and equipment during snow removal operations. <br /> The original salt storage building will be retrofitted to hold landscaping materials, such as black dirt,wood chips, <br /> ag lime, etc. <br /> Funding Source: <br /> PW Facility Contingency Fund-estimated balance of$1.2 million <br /> Recommendation: <br /> Staff recommends accepting the bid from A&B construction in the amount of$469,110.00 for construction of salt <br /> storage building at 14199 Jaspar Street <br /> Outcome/Action: <br /> Motion to adopt Resolution#22-059 accepting bids and awarding a contract for construction of Improvement <br /> Project#20-07, construction of salt storage building at 14199 Jaspar St by A&B Construction in the amount of$ <br /> 469,110.00. <br /> Attachments <br /> Resolution#22-059 <br /> Proposed Salt Shed <br /> Form Review <br /> Inbox Reviewed By Date <br /> Kurt Ulrich Kurt Ulrich 03/03/2022 10:16 AM <br /> Form Started By:Grant Riemer Started On:02/25/2022 11:58 AM <br /> Final Approval Date:03/03/2022 <br />