reconstructing Center Street between 146h Avenue and Bunker Lake Boulevard, as well as appurtenant sidewalk,
<br /> trail and municipal utilities construction.
<br /> Attached is a figure showing the proposed COR Infrastructure Improvements, as well as final plans. All streets,
<br /> sidewalks and trails were designed in coordination with the COR Mass Grading final elevations.
<br /> A total of eleven(11)bids were publicly opened and tabulated on March 13, 2024, and the following bids were
<br /> found to comply with the approved plans and specifications and advertisements for bids.
<br /> Company Bid
<br /> Douglas-Kerr Underground, L.L.C. $2,973,047.22
<br /> North Pine Aggregate,Inc. $2,979,501.93
<br /> Kuechle Underground Inc. $2,990,169.39
<br /> Northdale Construction Company, Inc. $3,112,007.72
<br /> Northern Lines Contracting $3,140,130.81
<br /> New Look Contracting,Inc. $3,233,282.36
<br /> Burschville Construction Inc. $3,268,421.16
<br /> Dave Perkins Contracting Inc. $3,294,952.51
<br /> Park Construction Company $3,399,091.21
<br /> Northwest $3,600,733.24
<br /> Meyer Contracting Inc. $3,693,339.41
<br /> Engineer's Estimate $3,651,888.05
<br /> Bids were generally competitive and Douglas-Kerr Underground, L.L.C. submitted the lowest responsible bid in
<br /> the amount of$2,973,047.22 for the total bid for construction of the improvements in accordance with the
<br /> approved plans and specifications and advertisements for bids. The bid of Douglas-Kerr Underground,L.L.C. was
<br /> On March 26, 2024, the City Council will be asked to award a construction contract to Douglas-Kerr
<br /> Underground, L.L.C. in the amount of$2,973,047.22. Staff is requesting a recommendation to City Council from
<br /> the Public Works Committee for awarding this construction contract.
<br /> Notification:
<br /> Bid advertisements were published in the Anoka Union Herald on Friday, February 16th, and Friday, February
<br /> 23rd, 2024.
<br /> Time Frame/Observations/Alternatives:
<br /> Time Frame:
<br /> Staff anticipates less than 10 minutes will be required to present this case and respond to questions.
<br /> Observations:
<br /> Tentative project schedule:
<br /> •March 26th- Council considers award of contract
<br /> •April/May- Start construction
<br /> •August 30th- Substantial completion
<br /> •October 18th -Final completion
<br /> Alternatives:
<br /> Alternative#1: Motion recommending City Council acceptance of bids and award of a contract for construction
<br /> for Improvement Project#23-19, COR hifrastructure Improvements, to Douglas-Kerr Underground, L.L.C. in the
<br /> amount of$2,973,047.22.
<br />
|