' <br />June 29, 1985 City of Ramsey' Page 2 <br />' <br />4. Change Order No. 2. This C.O. did not come up until most of the work <br />on the project had been completed. We request a 4 day time extension <br />due to the number of operations involved and the curing time required. <br />In accordance <br />with 1806.2 of the specifications an automatic time extension <br />is due because of the Contract Overrun. We estimate the final contract <br />amount to be approximately $427,000, or an overrun of approximately $41,470. <br />This <br />yields and extension of 6.5 days as shown: <br />Original Contract Amount $385,530.00 <br />' <br />Original Contract Time 61 Cal. Days <br />Original Production per Day $6,320.16 <br />Contract Overrun t Production 6.5 days extension <br />It is our opinion that we made extraordinary efforts to meet the May 10th <br />deadline <br />and that the City has a good job at a very reasonable cost. The <br />City and the Developer have had full use of the streets and facilities <br />' <br />since June 21st, the date on which seeding and sodding was completed. <br />At this time we are not writing to submit a claim against the City for <br />additional work performed such as: a) excessive amounts of earthwork <br />"Subgrade <br />' <br />in Preparation" areas, b) restoration of utility trenches, <br />or a) additional costs due to interferences by other contractors. <br />' <br />In summary we request that the date for completion of all substantial work <br />be considered June 21, 1985, and that the contract completion date be <br />extended to June 21, 1985 due to the 27.5 day time extension which brings <br />us well past June 21st. <br />Sincerely, <br />FORES IAKE CONTRACTING, INC. <br />Richard Spengler Sec. <br />1 <br />